The potential benefits of a safety program are generally only realized after an incident has occurred. Resource allocation in an organization's safety program has the imperative task of balancing costs and often unrealized benefits. Management can be wary to allocate additional resources to a safety program because it is difficult to estimate the return on investment, especially since the returns are a set of negative outcomes not manifested. One way that safety professionals can provide an estimate of potential return on investment is to forecast how the organizations incident rate can be affected by implementing different resource allocation strategies and what the expected incident rate would have been without intervention. This study evaluates forecasting methods used to predict incidents against one another against a common definition of performance accuracy to identify the method that would be the most applicable to use as part of a safety resource allocation model. By identifying the most accurate forecasting method, the uncertainty of which method a safety professional should utilize for incident rate prediction is reduced. Incident data from the Mine Safety and Health Administration (MSHA) was used to make short- and long-term forecasts. The performance of each of these methods was evaluated against one another to ascertain which method has the highest level of accuracy, lowest bias, and best complexity-adjusted goodness-of-fit metrics. The double exponential smoothing and auto-regressive moving average (ARMA) statistical forecasting methods provided the most accurate incident rate predictions.
Skip Nav Destination
Article navigation
December 2017
Research-Article
Evaluating the Performance and Accuracy of Incident Rate Forecasting Methods for Mining Operations
Jason C. York,
Jason C. York
Department of Energy and Mineral Engineering,
The Pennsylvania State University,
University Park, PA 16802
e-mail: jcy127@gmail.com
The Pennsylvania State University,
University Park, PA 16802
e-mail: jcy127@gmail.com
Search for other works by this author on:
Jeremy M. Gernand
Jeremy M. Gernand
Mem. ASME
Department of Energy and Mineral Engineering,
The Pennsylvania State University,
University Park, PA 16802
e-mail: jmg64@psu.edu
Department of Energy and Mineral Engineering,
The Pennsylvania State University,
University Park, PA 16802
e-mail: jmg64@psu.edu
Search for other works by this author on:
Jason C. York
Department of Energy and Mineral Engineering,
The Pennsylvania State University,
University Park, PA 16802
e-mail: jcy127@gmail.com
The Pennsylvania State University,
University Park, PA 16802
e-mail: jcy127@gmail.com
Jeremy M. Gernand
Mem. ASME
Department of Energy and Mineral Engineering,
The Pennsylvania State University,
University Park, PA 16802
e-mail: jmg64@psu.edu
Department of Energy and Mineral Engineering,
The Pennsylvania State University,
University Park, PA 16802
e-mail: jmg64@psu.edu
Manuscript received January 28, 2016; final manuscript received March 16, 2017; published online June 13, 2017. Assoc. Editor: Mohammad Pourgol-Mohammad.
ASME J. Risk Uncertainty Part B. Dec 2017, 3(4): 041001 (16 pages)
Published Online: June 13, 2017
Article history
Received:
January 28, 2016
Revised:
March 16, 2017
Citation
York, J. C., and Gernand, J. M. (June 13, 2017). "Evaluating the Performance and Accuracy of Incident Rate Forecasting Methods for Mining Operations." ASME. ASME J. Risk Uncertainty Part B. December 2017; 3(4): 041001. https://doi.org/10.1115/1.4036309
Download citation file:
Get Email Alerts
Cited By
Paradox of Optimal Learning: An Info-Gap Perspective
ASME J. Risk Uncertainty Part B
Robust Design Optimization of Expensive Stochastic Simulators Under Lack-of-Knowledge
ASME J. Risk Uncertainty Part B (June 2023)
Sequential Ensemble Monte Carlo Sampler for On-Line Bayesian Inference of Time-Varying Parameter in Engineering Applications
ASME J. Risk Uncertainty Part B (September 2023)
Probabilistic Validation: Theoretical Foundation and Methodological Platform
ASME J. Risk Uncertainty Part B (June 2023)
Related Articles
An Assessment of Overburden Stability in the In-Situ Gasification of Texas Lignite
J. Pressure Vessel Technol (August,1978)
Risk Assessment Methodology for Electric-Current Induced Drowning Accidents
ASME J. Risk Uncertainty Part B (September,2016)
Accuracy Analysis of Parallel Manipulators With Joint Clearance
J. Mech. Des (January,2009)
Identifying Structural Breaks in Stochastic Mortality Models
ASME J. Risk Uncertainty Part B (June,2015)
Articles from Part A: Civil Engineering
Climate and Related Uncertainties Influencing Research and Development Priorities
ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering (June,2015)
Mental Models of Navigation Safety to Inform Risk Management Decisions: Case Study on the Houston Ship Channel
ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering (September,2018)
Multicriteria Decision Analysis Approach for Stochastic Ranking with Application to Network Resilience
ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering (March,2016)
Asset Risk Management and Resilience for Flood Control, Hydropower, and Waterways
ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering (December,2016)
Related Proceedings Papers
Related Chapters
Image Smoothing Based on Game of Life
International Conference on Advanced Computer Theory and Engineering (ICACTE 2009)
Integration of Multiobjective Tradeoff Analysis with Cost-Benefit Analysis in the Allocation of Resources to System Safety (PSAM-0428)
Proceedings of the Eighth International Conference on Probabilistic Safety Assessment & Management (PSAM)
Scalable Video Streaming Multicast of Multiple Groups over Broadband Wireless Networks
International Conference on Computer Engineering and Technology, 3rd (ICCET 2011)